The Nio ET7 delivered around 3,000 units per month for most of the second half of 2022, but only 521 and 649 units were delivered in January and February of this year, respectively.
2023031301505885

The Nio ET7 delivered around 3,000 units per month for most of the second half of 2022, but only 521 and 649 units were delivered in January and February of this year, respectively.

Nio App no longer shows ET7 wait time as talk of revamped model heats up-CnEVPost

(From left to right: EC7, EC6, ET7, ET5. Screenshot on March 13.)

Past experience has shown that whenever Nio’s mobile app stops showing the wait time for a model, it means that the improved version of the model is not far from release.

The Nio App stopped showing the expected delivery date for the electric vehicle maker’s flagship sedan, the ET7, starting today, the first time the company’s model wait times have changed in the past month.

The Nio App is currently showing eight models, including the old ES8, ES6 and EC6 based on the NT 1.0 platform and the new ES8, ES7, EC7, ET7 and ET5 based on the NT 2.0 platform.

The EC7 coupe SUV and the new ES8 were launched at Nio Day 2022 held on December 24, 2022, with deliveries to begin in May and June 2023, respectively.

Wait times for all other Nio models remain unchanged today. The last change to this information was on February 14, when the wait times for both the ES7 and ET7 changed from the previous 3-4 weeks to about 3 weeks, and for the ET5 from about 3 weeks to 2-3 weeks.

Nio App no longer shows ET7 wait time as talk of revamped model heats up-CnEVPost

(From left to right: All-new ES8, old ES8, ES7, ES6. Screenshot on March 13.)

Nio’s latest move comes at a time when discussions on social media about a revamped version of the ET7 are on the rise.

In several WeChat groups where CnEVPost is present, some Nio followers are already anticipating a facelift of the sedan one year since deliveries began.

Longtime Nio follower and auto blogger @肉肉爸比ev hinted on March 10 that a revamped version of the ET7 is not far away.

“Are people that concerned about the ET7 facelift? Let’s just say the 2023 ET7 may be coming soon,” the blogger wrote.

Changes to the new ET7 will likely not be significant, and Nio may offer upgrade options to owners of the current model, the blogger said, adding that consumers interested in the ET7 may choose to wait and see in the short term.

Nio App no longer shows ET7 wait time as talk of revamped model heats up-CnEVPost

Nio launched the ET7, its first sedan, at the Nio Day 2020 event on January 9, 2021, with deliveries starting March 28, 2022.

In April 2022, the ET7’s first full month of delivery, the sedan was ranked No. 10 in a list of premium sedans starting at more than RMB 300,000 ($43,440) by the China Passenger Car Association (CPCA) with 693 retail sales.

With increased capacity, ET7 sales continued to grow after deliveries began and reached a new monthly high of 4,349 units in June 2022.

Deliveries of the ET7 remained around 3,000 units per month for the vast majority of the second half of last year, but in December deliveries slipped to 1,379 units, missing the CPCA’s ranking of premium sedan sales for the first time.

Nio stopped publishing ET7 figures in its monthly delivery figures this year, but figures released by the CPCA show that the sedan delivered 521 units in January and 649 units in February.

The CPCA’s figures come from the numbers reported by carmakers, and the ET7 sales figures in its monthly rankings are consistent with the available figures previously published by Nio.

Nio App no longer shows ET7 wait time as talk of revamped model heats up-CnEVPost

(1 $ = RMB 6.9063)

Nio ET5 drops 1 spot in ranking of top-selling premium sedans in China

Changes in wait times for Nio models

Date Model Prev Change Latest
20240601 ET7 (NT 2.0) 5-6 weeks Down 3-4 weeks
20240517 ET7 (NT 2.0) 7-8 weeks Down 5-6 weeks
20240509 ET7 (NT 2.0) 4-6 weeks Up 7-8 weeks
20240506 ES7 (NT 2.0) 4-5 weeks Down 3-5 weeks
20240506 EC7 (NT 2.0) 3-4 weeks Down 2-3 weeks
20240506 ES8 (NT 2.0) 3-4 weeks Down 2-3 weeks
20240425 ET7 (NT 2.0) NA Start showing
20240422 ET5 (NT 2.0) 3-4 weeks Down 2-3 weeks
20240422 ES8 (NT 2.0) 2-3 weeks Up 3-4 weeks
20240422 EC7 (NT 2.0) 2-3 weeks Up 3-4 weeks
20240416 ET5 (NT 2.0) 4-5 weeks Down 3-4 weeks
20240416 ES7 (NT 2.0) 6-7 weeks Down 4-5 weeks
20240408 ET5 (NT 2.0) 7-8 weeks Down 4-5 weeks
20240408 ES7 (NT 2.0) 7-8 weeks Down 6-7 weeks
20240325 ES7 (NT 2.0) 8-9 weeks Down 7-8 weeks
20240313 ET5 (NT 2.0) 9-11 weeks Down 7-8 weeks
20240313 ET5 Touring (NT 2.0) 2-4 weeks Down 2-3 weeks
20240313 ES6 (NT 2.0) 2-4 weeks Down 2-3 weeks
20240313 EC6 (NT 2.0) 2-4 weeks Down 2-3 weeks
20240313 EC7 (NT 2.0) 2-4 weeks Down 2-3 weeks
20240313 ES7 (NT 2.0) 11-13 weeks Down 8-9 weeks
20240313 ES8 (NT 2.0) 2-4 weeks Down 2-3 weeks
20240222 ET5 (NT 2.0) NA Start showing 9-11 weeks
20240222 ET5 Touring (NT 2.0) NA Start showing 2-4 weeks
20240222 ES6 (NT 2.0) NA Start showing 2-4 weeks
20240222 EC6 (NT 2.0) NA Start showing 2-4 weeks
20240222 EC7 (NT 2.0) NA Start showing 2-4 weeks
20240222 ET7 (NT 2.0) NA Start showing 2-4 weeks
20240222 ES7 (NT 2.0) NA Start showing 11-13 weeks
20240222 ES8 (NT 2.0) NA Start showing 2-4 weeks
20240202 ET5 (NT 2.0) 2-3 weeks NA Stop showing
20240202 ET5 Touring (NT 2.0) 2-3 weeks NA Stop showing
20240202 ES6 (NT 2.0) 2-3 weeks NA Stop showing
20240202 EC6 (NT 2.0) 2-3 weeks NA Stop showing
20240202 EC7 (NT 2.0) 2-3 weeks NA Stop showing
20240202 ET7 (NT 2.0) 4-5 weeks NA Stop showing
20240202 ES7 (NT 2.0) 4-5 weeks NA Stop showing
20240202 ES8 (NT 2.0) 2-3 weeks NA Stop showing
20240103 ET5 (NT 2.0) 3-4 weeks Down 2-3 weeks
20240103 ET5 Touring (NT 2.0) 3-4 weeks Down 2-3 weeks
20240103 EC7 (NT 2.0) 3-4 weeks Down 2-3 weeks
20240103 ES8 (NT 2.0) 3-4 weeks Down 2-3 weeks
20231220 ET5 (NT 2.0) 2-3 weeks Up 3-4 weeks
20231220 ET5 Touring (NT 2.0) 2-3 weeks Up 3-4 weeks
20231220 EC7 (NT 2.0) 2-3 weeks Up 3-4 weeks
20231220 ES8 (NT 2.0) 2-3 weeks Up 3-4 weeks
20231220 ET7 (NT 2.0) 5-6 weeks Down 4-5 weeks
20231220 ES7 (NT 2.0) 5-6 weeks Down 4-5 weeks
20231212 ET7 (NT 2.0) 4-5 weeks Up 5-6 weeks
20231212 ES7 (NT 2.0) 4-5 weeks Up 5-6 weeks
20231024 EC7 (NT 2.0) 3-4 weeks Down 2-3 weeks
20231024 ES8 (NT 2.0) 3-4 weeks Down 2-3 weeks
20231011 EC7 (NT 2.0) 4-5 weeks Down 3-4 weeks
20231011 ES8 (NT 2.0) 4-5 weeks Down 3-4 weeks
20231008 ET5 (NT 2.0) 4-5 weeks Down 2-3 weeks
20231008 ET5 Touring (NT 2.0) 4-5 weeks Down 2-3 weeks
20231008 ES6 (NT 2.0) 3-4 weeks Down 2-3 weeks
20231008 EC6 (NT 2.0) 3-4 weeks Down 2-3 weeks
20231008 EC7 (NT 2.0) 3-4 weeks Up 4-5 weeks
20231008 ES8 (NT 2.0) 5-6 weeks Down 4-5 weeks
20230918 EC6 (NT 2.0) New Model NA 3-4 weeks
20230914 ET5 (NT 2.0) About 3 weeks Up 4-5 weeks
20230914 ET5 Touring (NT 2.0) About 3 weeks Up 4-5 weeks
20230914 EC7 (NT 2.0) About 4 weeks Down 3-4 weeks
20230914 ES8 (NT 2.0) 6-7 weeks Down 5-6 weeks
20230901 ES8 (NT 2.0) 8-9 weeks Down 6-7 weeks
20230803 ET7 (NT 2.0) 6-7 weeks Down 4-5 weeks
20230803 ES6 (NT 2.0) 3-6 weeks Down 3-4 weeks
20230803 ES7 (NT 2.0) 6-7 weeks Down 4-5 weeks
20230803 ES8 (NT 2.0) NA Start showing 8-9 weeks
20230705 ES7 (NT 2.0) 6-8 weeks Down 6-7 weeks
20230705 ES6 (NT 2.0) 3-4 weeks Up 3-6 weeks
20230705 ET7 (NT 2.0) 6-8 weeks Down 6-7 weeks
20230705 ET5 Touring (NT 2.0) 3-4 weeks Down About 3 weeks
20230701 ES8 (NT 2.0) June Stop showing NA
20230626 ES7 (NT 2.0) About 3 weeks Up 6-8 weeks
20230626 ES6 (NT 2.0) About 5 weeks Down 3-4 weeks
20230626 ET7 (NT 2.0) About 3 weeks Up 6-8 weeks
20230616 ET5 Touring (NT 2.0) NA Start showing 3-4 weeks
20230613 ES7 (NT 2.0) 3-4 weeks Down About 3 weeks
20230613 EC7 (NT 2.0) About 5 weeks Down About 4 weeks
20230613 ET7 (NT 2.0) 3-4 weeks Down About 3 weeks
20230606 ES6 (NT 2.0) NA Start showing About 5 weeks
20230605 ES7 (NT 2.0) About 3 weeks Up 3-4 weeks
20230605 ET7 (NT 2.0) About 3 weeks Up 3-4 weeks
20230601 ET5 (NT 2.0) 2-3 weeks Up About 3 weeks
20230601 EC7 (NT 2.0) 5-7 weeks Down About 5 weeks
20230601 ES7 (NT 2.0) About 4 weeks Down About 3 weeks
20230530 ES6 (NT 2.0) May Stop showing NA
20230524 ES6 (NT 2.0) NA Start showing May
20230516 ET5 (NT 2.0) About 2 weeks Up 2-3 weeks
20230516 EC7 (NT 2.0) About 5 weeks Up 5-7 weeks
20230509 ES7 (NT 2.0) About 3 weeks Up About 4 weeks
20230428 ET7 (NT 2.0) About 4 weeks Down About 3 weeks
20230428 EC7 (NT 2.0) About 4 weeks Up About 5 weeks
20230425 ES7 (NT 2.0) 3-5 weeks Down About 3 weeks
20230421 ET7 (NT 2.0) NA NA About 4 weeks
20230421 EC7 (NT 2.0) Mid May NA About 4 weeks
20230417 ES7 (NT 2.0) About 2 weeks Up 3-5 weeks
20230414 ES6 (NT 1.0) About 2 weeks NA Stop showing
20230410 ET5 (NT 2.0) About 3 weeks Down About 2 weeks
20230410 ES7 (NT 2.0) About 3 weeks Down About 2 weeks
20230328 ET5 (NT 2.0) 3-4 weeks Down About 3 weeks
20230328 ES7 (NT 2.0) 4-6 weeks Down About 3 weeks
20230314 ET5 (NT 2.0) 2-3 weeks Up 3-4 weeks
20230314 ES7 (NT 2.0) About 3 weeks Up 4-6 weeks
20230313 ET7 (NT 2.0) About 3 weeks NA Stop showing
20230214 ES7 (NT 2.0) 3-4 weeks Down About 3 weeks
20230214 ET7 (NT 2.0) 3-4 weeks Down About 3 weeks
20230214 ET5 (NT 2.0) About 3 weeks Down 2-3 weeks
20230206 ET5 (NT 2.0) 3-4 weeks Down About 3 weeks
20230128 ES7 (NT 2.0) 2-3 weeks Up 3-4 weeks
20230128 ET7 (NT 2.0) 2-3 weeks Up 3-4 weeks
20230128 ET5 (NT 2.0) 7-9 weeks Down 3-4 weeks
20230111 ET5 (NT 2.0) 8-10 weeks Down 7-9 weeks
20230105 ET5 (NT 2.0) 9-11 weeks Down 8-10 weeks
20221229 ET5 (NT 2.0) 10-12 weeks Down 9-11 weeks
20221222 ET5 (NT 2.0) 12-14 weeks Down 10-12 weeks
20221220 ES7 (NT 2.0) 4-6 weeks Down 2-3 weeks
20221213 ET5 (NT 2.0) 13-15 weeks Down 12-14 weeks
20221213 ET7 (NT 2.0) About 2 weeks Up 2-3 weeks
20221213 EC6 (NT 1.0) About 2 weeks NA Stop showing
20221125 ET5 (NT 2.0) 21-23 weeks Down 13-15 weeks
20221125 ES7 (NT 2.0) 7-9 weeks Down 4-6 weeks
20221125 ET7 (NT 2.0) 3-5 weeks Down About 2 weeks
20221123 ES8 (NT 1.0) About 2 weeks NA Stop showing
20221116 ET7 (NT 2.0) 4-6 weeks Down 3-5 weeks
20221110 ES8 (NT 1.0) 2-3 weeks Down About 2 weeks
20221110 ES6 (NT 1.0) 2-3 weeks Down About 2 weeks
20221110 EC6 (NT 1.0) 2-3 weeks Down About 2 weeks
20221103 ES7 (NT 2.0) 11-13 weeks Down 7-9 weeks
20221103 ET7 (NT 2.0) 6-8 weeks Down 4-6 weeks
20221103 ES8 (NT 1.0) 2-4 weeks Down 2-3 weeks
20221103 ES6 (NT 1.0) 2-4 weeks Down 2-3 weeks
20221103 EC6 (NT 1.0) 2-4 weeks Down 2-3 weeks
20221031 ES7 (NT 2.0) 12-14 weeks Down 11-13 weeks
20221031 ES8 (NT 1.0) 3-5 weeks Down 2-4 weeks
20221031 ES6 (NT 1.0) 3-5 weeks Down 2-4 weeks
20221031 EC6 (NT 1.0) 3-5 weeks Down 2-4 weeks
20221021 ES7 (NT 2.0) 13-15 weeks Down 12-14 weeks
20221021 ET7 (NT 2.0) 11-13 weeks Down 6-8 weeks
20221021 ET5 (NT 2.0) 21-23 weeks NA Stop showing
20221021 ES8 (NT 1.0) 4-6 weeks Down 3-5 weeks
20221021 ES6 (NT 1.0) 4-6 weeks Down 3-5 weeks
20221021 EC6 (NT 1.0) 4-6 weeks Down 3-5 weeks


Previous Article

2023 Bajaj Pulsar 200 NS USD Forks Walkaround – Arrives At Dealer Showroom

Next Article

Hyundai India’s Potential Acquisition of General Motors Talegaon plant

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our Newsletter

Subscribe to our email newsletter to get the latest posts delivered right to your email.
Pure inspiration, zero spam ✨